Articles #195 to #202 in this series took readers through supplier verification, sourcing, quality control, compliance, packaging and shipping, warranty and after-sales service. This article explains how to turn an idea or product brief into a manufacturable, tested, production-ready electronics product.
The central question is: how can an overseas buyer work with a Chinese factory to develop a new electronics product without losing control of the product requirements, design ownership, development budget, schedule, quality or production readiness?
The process is organised around stage gates: each stage has defined deliverables, and the buyer approves each gate before the project advances. Design approval and manufacturing readiness are different things: a product can be designed correctly and still not be manufacturable at scale.
The article follows one hypothetical product throughout: a rechargeable Bluetooth sensor device with a printed circuit board, a lithium battery, a plastic enclosure and a companion app. The product is simple enough to follow and complex enough to show every stage: briefing, feasibility, contract, specification, design, prototype, validation, documentation, pilot run and release. It is an illustrative example, not a real product.
1. Understand What Kind of Product-Development Project You Are Undertaking
Product development is not the same as product sourcing or OEM/ODM selection. A factory may offer an existing product, modify an existing design, or develop a genuinely new product. The buyer must know which one is being offered, because the cost, risk and ownership implications are completely different.
Four kinds of project
| Project type | What the factory does | What the buyer controls |
|---|---|---|
| Private label | Sells an existing product under the buyer's brand, possibly with limited changes such as packaging or a logo | Brand, packaging and agreed product options |
| OEM | Manufactures a product to the buyer's design or specification | Buyer-supplied design and specification, subject to the contract |
| ODM | Adapts or develops a product using the manufacturer's design and engineering capabilities | The brief and agreed acceptance criteria; design ownership and licensing depend on the contract |
| Custom product development | Engineers a new product or a substantial redesign for the buyer | The requirements; ownership of resulting design rights must be expressly agreed |
These labels are used inconsistently by suppliers. OEM and ODM are not universal legal or technical categories, and the labels do not determine legal ownership — the contract does. A factory that says "ODM" may mean it will change the colour of an existing enclosure, or it may mean it will design a new circuit board from scratch. Tell the reader to ask what work the factory will actually perform. Developing a new PCB, modifying an existing enclosure, changing firmware, and putting a buyer's logo on an existing product are different levels of development, with different costs, risks and ownership implications.
The question to ask first
Before discussing price, ask the factory: "What exactly will you design, what will you reuse from an existing product, and what will you buy in?" The answer separates a development partner from a reseller. A supplier that cannot explain who will perform the engineering, what will be developed and what will be reused from an existing product is not a suitable development partner for that project.
2. Prepare a Product Brief Before Contacting Factories
A factory cannot quote a development project it does not understand. The buyer should prepare a product brief before requesting a development proposal. A target price without a defined specification is not a reliable development budget.
What the brief should contain
| Item | What to write |
|---|---|
| Product purpose and target users | Who uses it and what problem it solves |
| Intended countries and markets | Where the product will be sold, which regulatory requirements apply, and which entity will place it on each market under whose name or trademark |
| Core functions and performance | What it must do, in measurable terms where possible |
| Reference products and sketches | Photos, sketches or preliminary designs |
| Size, weight, materials and appearance | Physical constraints and finish |
| Power, battery and charging | Battery type, capacity, charging method and expected operating time |
| Connectivity and software | Wireless protocols, interfaces, app and cloud requirements |
| Target retail price and target cost | The commercial envelope the design must fit |
| Expected volume and forecast | First order and annual volume |
| Required launch date | The schedule the project must meet |
| Environment and operating conditions | Temperature, humidity, water resistance and use conditions |
| Product lifecycle | Expected commercial life, support period and whether future hardware revisions are anticipated |
| Software and cloud | Whether the app uses a cloud service, who hosts it, who owns the account and what happens if the service ends |
| Security and updates | Firmware update mechanism, security-support period and responsibility for vulnerabilities |
| Cost assumptions | Whether the target cost includes packaging, testing, accessories and other components |
For the hypothetical sensor device, the brief might say: a rechargeable Bluetooth temperature and humidity sensor for indoor use, battery life of at least six months at one measurement every ten minutes at 25 degrees Celsius, with the battery considered exhausted when its voltage falls below the cut-off specified in the requirements, an enclosure no larger than 60 mm in diameter, a companion app for iOS and Android, a target EXW unit cost at a specified production volume, with the named place and applicable Incoterms rule agreed in the quotation, excluding development fees, tooling, certification and freight, and a first order of 5,000 units. Every item in that sentence is a requirement the factory can quote against. A brief that says only "a smart sensor, good quality, low price" is not.
The output of this stage
A product brief and a preliminary requirements document. These are the documents the factory quotes against and the buyer later measures the product against. If the brief is vague, the quotation is vague, and the disputes later are about what was never written down.
3. Check Feasibility Before Paying for Development
Feasibility is the stage where the buyer finds out whether the idea can be developed within the budget, schedule and technical constraints — before committing to full development, tooling or production expenditure. A factory may charge for a preliminary feasibility study, but its fee, deliverables and go/no-go criteria should be agreed in advance. A supplier that simply says "Yes, we can do it" has not done a feasibility assessment.
What to assess
- Technical feasibility: can the functions be built with available technology?
- Component availability and lifecycle: are the key parts in production, and for how long?
- Existing reference designs and development platforms: what can be reused?
- Mechanical and tooling complexity: how hard is the enclosure to make?
- Battery capacity and thermal constraints: will the battery fit, and will the device stay cool?
- Wireless and connectivity requirements: which radio, which antenna, which certification?
- Manufacturing complexity and expected yield: how hard is it to build reliably?
- Target cost at realistic production volumes: does the cost work at the forecast volume?
- Regulatory and certification implications: which markets, which rules?
For the sensor device, feasibility questions include whether a six-month battery life is realistic with the chosen Bluetooth radio and reporting interval, whether the enclosure can be injection-moulded at the target cost, and whether the chosen battery is available from more than one supplier. Ask the factory to identify assumptions, technical risks, unresolved questions and items excluded from the quotation.
The output of this stage
A feasibility report, a preliminary bill of materials (BOM) and a development quotation. The preliminary BOM is the first costed list of parts; it is where the target cost is tested against reality. If the preliminary BOM already exceeds the target cost, the buyer should change the specification now, not after tooling is cut. A preliminary BOM is not a guaranteed final production price: it is the first costed list of parts, and the price can move as the design, the components and the volumes change.
The feasibility report should finish with a written go/no-go recommendation. It should state what is technically achievable, what assumptions remain unverified, which components present sourcing or lifecycle risks, which compliance tests may be required, what the estimated development cost and schedule are, and what must happen before the buyer commits to tooling.
4. Choose the Right Factory and Engineering Team
The factory that can manufacture an existing product is not necessarily capable of developing a new one. Manufacturing skill and engineering skill are different capabilities, and a buyer who confuses them will discover the difference mid-project.
What to assess
| Capability | What to check |
|---|---|
| Electronics engineers | In-house engineers, not only production staff |
| Firmware and software | Who writes the firmware, and who maintains it |
| Mechanical and industrial design | Enclosure, tooling and appearance capability |
| Prototype and testing facilities | Can the factory build and test prototypes in-house |
| Experience with similar products | Comparable products developed, not only manufactured |
| Specialist laboratories | Access to EMC, radio, safety and environmental testing |
| Component sourcing | How components are selected and qualified |
| Engineering-change controls | How design changes are recorded and approved |
| Subcontracting | Whether development is performed in-house or subcontracted |
Ask who will be the project manager and who is technically responsible for each engineering discipline. A trading company may coordinate development, but the buyer should know which company actually performs the engineering work. If the engineering is subcontracted to a design house the buyer has never met, the buyer should know that before signing, not after the first prototype fails.
The output of this stage
A documented capability assessment and a project responsibility matrix: one named person responsible for electronics, one for firmware, one for mechanical design, one for testing, and one project manager who coordinates them. The matrix should distinguish in-house engineering, subcontracted engineering, project management and manufacturing responsibility, and it should name the external engineering partner where one is used. What matters is transparency, capability and accountability, not whether every engineer sits on the factory's payroll. The method for assessing the factory itself is in How to Verify an Electronics Supplier in China: Factory Audits, Trading Companies and Red Flags.
5. Agree the Development Contract, Budget and Intellectual-Property Ownership
This is one of the article's most important sections. The development contract decides who owns what, who pays for what, and what happens when the project fails. A buyer who signs a purchase order for prototypes without a development agreement has agreed to pay for work without agreeing who owns the result.
What the contract should cover
- Development scope and deliverables: exactly what the factory will produce.
- One-time engineering or NRE (non-recurring engineering) fees.
- Prototype and tooling charges.
- Payment milestones tied to deliverables, not to calendar dates alone.
- Number of included design revisions, and the cost of additional changes.
- What happens if technical feasibility fails.
- Ownership or licensing of designs and technology.
- Confidentiality and permitted use of information.
- Ownership of custom tooling and moulds.
- Rights to use another factory for production.
- Access to source files, firmware and technical documentation.
- Termination, handover and dispute provisions.
- Background IP licence: what rights the buyer receives to use the factory's pre-existing technology.
- Subcontractor IP: the factory must secure the necessary rights from every subcontractor.
- Third-party software: proprietary libraries, SDKs and open-source components and their licences.
- Derivative works and improvements: who owns them and whether the buyer can continue using them.
- Source-code delivery: the delivery format, build instructions, toolchain and dependencies.
- Source-code escrow: an escrow arrangement where the factory will not transfer source code immediately.
- Patent applications: who files, who pays and who controls prosecution.
- Rights after termination: the buyer can use already-created deliverables even if the project ends early.
If source-code escrow is used, the contract should identify the independent escrow agent, specify the release conditions, require updated deposits after material software releases, and provide for verification that the deposited source code can be built. The deposit should include the relevant toolchain, dependencies, build instructions and other materials needed to maintain the software. Release triggers may include insolvency, permanent discontinuation of support or an uncured material breach of the maintenance agreement. The buyer should also have an express licence to use and modify the released materials.
Who owns what: four kinds of IP
| Kind | What it is | Who owns it by default |
|---|---|---|
| Background IP | Technology and designs already owned by either party before the project | The party that already owned it |
| Project IP | New work created during the project | Depends on the right and the contract — see below |
| Third-party IP | Licensed components, software and technology | The licensor, under the licence terms |
| Improvements | Changes made to existing technology during development | Depends on the contract |
Commissioned inventions: the party that makes the invention generally holds the patent-application right by default
Do not let the buyer assume that paying a development fee automatically gives them ownership of everything created. Under Article 8 of China's Patent Law, for an invention-creation accomplished by an entity in execution of a commission given by another entity, the right to apply for a patent belongs, unless otherwise agreed, to the entity that accomplished the invention-creation — that is, the party that did the work, not the party that paid for it. After the application is approved, the applicant becomes the patentee. (Patent Law of the People's Republic of China, Article 8)
Paying for the work is not the test; doing the work is. If the factory itself is the entity that performs the commissioned inventive work, the default will generally place the patent-application right with that entity. If the factory subcontracts the inventive work, however, the initial entitlement may lie with the actual engineering subcontractor or another party that accomplished the invention-creation. The buyer should therefore require a complete chain of contractual rights from the factory and every relevant contributor, rather than assume that the contracting factory automatically owns every development result. The statutory opening is real: Article 8 applies "unless otherwise agreed", so an ownership clause in the development contract is effective.
Article 6 adds a second layer. For a service invention — an invention made by an employee in the performance of their employment duties, or mainly using the employer's material and technical means — the right to apply for a patent generally belongs to the employer. The buyer should therefore not rely solely on a clause saying that the factory assigns its rights. The buyer should also confirm that the factory has obtained the necessary rights from its employees, subcontractors and other contributors.
Under Article 10, an assignment of the right to apply for a patent or an existing patent right requires a written contract and registration with the patent administration department, and the assignment takes effect on the date of registration. A transfer by a Chinese entity or individual to a foreign party must go through the formalities in accordance with the relevant laws and administrative regulations. (Patent Law of the People's Republic of China, Articles 6, 8 and 10)
The Chinese Civil Code also contains important provisions governing technology-development contracts. Article 858 requires the parties to agree on the allocation of risks arising from insurmountable technical difficulties that cause development to fail, wholly or partly. If the agreement is absent or unclear and the issue cannot be resolved under Article 510, the risk is shared reasonably between the parties. A party that becomes aware of circumstances likely to cause development failure must promptly notify the other party and take appropriate measures to mitigate losses; if it fails to do so and the loss increases, it is liable for the additional loss. Article 859 addresses inventions resulting from commissioned development. Unless otherwise agreed or provided by law, the patent-application right belongs to the researcher-developer. If the researcher-developer obtains the patent, the client may exploit it in accordance with law. If the researcher-developer proposes to transfer the patent-application right, the client has a priority right to acquire it on equivalent terms. Article 860 addresses cooperative development. Unless otherwise agreed, the patent-application right for an invention resulting from cooperative development belongs jointly to all parties. A party proposing to transfer its share must give the other parties a priority right to acquire it on equivalent terms. The article also addresses situations where a party waives its share or does not agree to apply for a patent. Article 861 concerns technical know-how resulting from commissioned or cooperative development. The parties should agree on the rights to use and transfer the resulting work product. If there is no agreement or it is unclear, and the issue cannot be resolved under Article 510, all parties generally have the rights to use and transfer the work product before a patent right is granted for the same technical solution. However, in commissioned development, the researcher-developer cannot transfer the work product to a third party before delivering it to the client. These default rules are important reasons to agree expressly on patent rights, know-how, licensing and delivery obligations in the development contract rather than assume that payment alone gives the buyer exclusive ownership or control.
Copyright: the commissioned party owns it by default
Under Article 19 of China's Copyright Law (amended 2020, in force 1 June 2021), ownership of copyright in a commissioned work should be stipulated in a contract between the commissioning party and the commissioned party. Where there is no explicit stipulation in the contract or no contract is concluded, the copyright belongs to the commissioned party. (Copyright Law of the People's Republic of China, Article 19)
The commissioned party might be a factory, a design company or another legal entity, not necessarily an individual engineer. There is another qualification: Article 18 deals with works for hire — works created by a natural person in the fulfilment of tasks assigned by a legal person or unincorporated organisation. As a rule the copyright in such a work belongs to the author, but for engineering design drawings, product design drawings, maps and computer software created mainly with the employer's material and technical resources and under its responsibility, the author keeps the right of authorship while the employer enjoys the other rights. For an overseas buyer, the practical point is the same: do not assume that paying the development fee transfers copyright. Physical delivery of a design file does not, by itself, transfer copyright. A buyer receiving PCB layout files without copyright ownership or a sufficiently broad licence may not have the right to reproduce, modify, distribute or authorise another factory to manufacture from those files. The development agreement should expressly grant the buyer the rights needed to use, modify, reproduce and transfer the files to alternative manufacturers. Copyright in the files, patent rights in any underlying invention and rights in technical know-how are separate matters.
For ordinary works created in the course of employment, Article 18 also gives the employer priority to use the work within the scope of its professional activities. During the two years following completion, the author generally cannot authorise a third party to exploit the work in the same manner as the employer without the employer's consent. The special rule for engineering design drawings, product design drawings and computer software is particularly important in electronics development: where the statutory conditions are met, the author retains the right of authorship while the employer enjoys the other copyright rights.
Software: the commissioned developer owns it by default
The same rule applies to firmware and software. Under Article 11 of the Regulations on Computer Software Protection, where software is developed on commission, the copyright ownership shall be agreed upon in a written contract between the commissioning and the commissioned parties; in the absence of a written contract or an explicit agreement in the contract, the copyright shall be enjoyed by the commissioned party. (Regulations on Computer Software Protection, Article 11)
Firmware and software source code may be essential to future production and maintenance. A buyer who cannot obtain the source code cannot fix a bug, change a supplier or update the product without the original developer. Copyright ownership, delivery of source code and the right to maintain or modify software are separate matters. A buyer should address all three in the contract: a buyer might receive a licence to use firmware without owning its copyright, and might receive a binary without the source code needed to maintain it. Article 13 of the same Regulations adds that software developed by a natural person in the course of employment belongs to the employer in defined circumstances, including where the software is a foreseeable result of the employee's work or is developed mainly with the employer's resources.
Trade secrets and confidentiality
A confidentiality clause alone is not a complete IP-protection strategy. Under Article 10 of China's Anti-Unfair Competition Law, as revised in 2025 and in force from 15 October 2025, a trade secret is technical, business or other commercial information that is not known to the public, has commercial value and is subject to corresponding confidentiality measures taken by the rights holder. The State Administration for Market Regulation's Provisions on the Protection of Trade Secrets, in force from 1 June 2026, set out the confidentiality measures regulators recognise. The practical recommendations are the same: limit who sees the design, mark documents confidential, and control what leaves the factory. Many overseas buyers use a China-focused NNN agreement covering non-disclosure, non-use and non-circumvention, and should take advice on governing law, forum and enforceability for the specific transaction. NNN is a commercial description of the contractual protections being sought, not a guarantee of enforceability. The agreement should identify the correct Chinese contracting entity, clearly define prohibited uses and disclosures, address subcontractors and include appropriate governing-law and dispute-resolution provisions. Its practical enforceability depends on the drafting, parties, applicable law and available remedies. The agreement should state what the factory may not do with the buyer's information, not only what it may not disclose.
Tooling and prototypes
Ownership of the mould or prototype is distinct from ownership of the IP embodied in it. The contract should state who owns custom tooling and moulds, where they are stored, who maintains them, who can use them, and what happens to them if production moves to another factory. A buyer who pays for a mould but does not obtain clear contractual ownership and access rights may face difficulty proving ownership, obtaining possession of the tooling or transferring it to another factory.
The output of this stage
A signed development agreement, an IP schedule, a confidentiality agreement and a deliverables list. The IP schedule should list, item by item, who owns or licenses each deliverable:
| Deliverable | Ownership or licence question |
|---|---|
| Circuit schematic | Who owns the copyright and may modify it? |
| PCB layout | Can another factory manufacture from it? |
| Firmware source code | Is it transferred, licensed or escrowed? |
| Mobile app source code | Who owns it and the associated build environment? |
| Cloud/backend software | Who owns the code, accounts and data infrastructure? |
| Mechanical CAD | Can the buyer modify and reproduce it? |
| Mould and tooling | Who owns the physical asset? |
| Test fixtures and scripts | Can another factory use them? |
| Third-party libraries | What licence restrictions apply? |
6. Define the Technical Specification and Freeze the Requirements
A product idea becomes a development project when it becomes a specification: a set of measurable requirements the factory can build to and the buyer can test against.
What the specification should contain
- Functional requirements: what the product does.
- Electrical specifications: voltages, currents, power consumption.
- Mechanical dimensions and tolerances.
- Materials and finish.
- Performance and environmental requirements.
- Battery and charging specifications.
- Firmware behaviour and update requirements.
- Connectivity and interoperability.
- User interface and language requirements.
- Safety and regulatory requirements.
- Packaging and labelling requirements.
Make requirements testable
The difference between a requirement such as "long battery life" and a testable requirement such as "battery life of at least six months under an agreed test profile, including one measurement every ten minutes, specified Bluetooth advertising and connection behaviour, transmit power, operating-temperature conditions, battery chemistry and capacity, and a defined end-of-life voltage" is the difference between an argument and a test. The requirements document must specify the test method and acceptance criteria so that the factory cannot use a different operating profile to demonstrate compliance. Each requirement should have a corresponding verification method: this is a requirements traceability matrix, and it is what turns the specification into an acceptance test.
For the sensor device, "the app connects reliably" is not a requirement. "The device pairs with the app within 30 seconds on first setup and reconnects within 10 seconds after the app restarts, tested on specified phone models running specified OS versions, over Bluetooth 5.0 at a distance of 3 metres, at 25 degrees Celsius, with five repetitions; a pairing counts as successful when the app shows the device connected, and a reconnection counts as failed if it takes longer than 10 seconds or requires the user to re-enter pairing mode" is a requirement, because it can be tested and failed. A testable requirement needs a test procedure, not merely a number.
Freeze, then change by procedure
The specification should be version-controlled. Changes after approval should go through a documented change process: who requested the change, what it costs, what it does to the schedule, and who approved it. For critical components, materials or design features, a change needs the buyer's prior written approval, not just a notification. A specification that changes by chat message is not a specification. The RFQ discipline that applies here — asking for warranty and spare-parts terms before comparing quotations — is part of a proper RFQ: the method is in Electronics Supplier Quotation and RFQ Checklist: How to Compare Factory Prices from China.
The output of this stage
An approved product specification, a requirements matrix and an initial product risk list. The risk list records what could go wrong — a component going end-of-life, a battery failing a safety test, a radio failing certification — and what the project will do about each risk.
7. Develop the Electronics, Firmware and Mechanical Design
This section explains the main engineering work without turning the article into a technical textbook. The buyer does not need to design the circuit; the buyer needs to review the important design decisions before they become expensive to change.
The engineering work
- Electronic architecture and component selection.
- Schematic and PCB layout.
- Mechanical enclosure and industrial design.
- Firmware and embedded software.
- Power management and thermal design.
- Antenna and wireless integration where applicable.
- Design for manufacturing (DFM): can the design be built efficiently?
- Design for assembly (DFA): can it be assembled without error?
- Design for test (DFT): can it be tested quickly on the production line?
- Component lifecycle and second-source planning: will the parts still exist in two years?
Review decisions early
A low-cost component that is difficult to source, has a short lifecycle or creates a compliance problem may cost more over the product's life than a slightly more expensive alternative. The buyer should review component choices, the antenna design, the battery and charging circuit, and the enclosure tooling plan before the factory commits to them. For the sensor device, the choice between a Bluetooth module and a chip-down radio design is a decision with cost, certification and second-source consequences that should be made deliberately, not discovered at the prototype stage.
Component sourcing matters here: the Huaqiangbei markets can supply reference designs and alternative components, but traceability and counterfeit risk must be managed. The guide is in Huaqiangbei Sourcing Tour in Shenzhen: A Practical Guide for Overseas Electronics Buyers.
Do not forget the app and the cloud
The hypothetical product includes an iOS and Android app, and the engineering section should cover it. Add mobile application development, cloud or backend development where applicable, API ownership and documentation, account and hosting ownership, third-party software licences, and software updates and security maintenance. A buyer may own the PCB design but still be unable to operate the product independently if the app, cloud service or backend is controlled by the factory. The requirements should also identify what personal or operational data the product collects, who determines the purposes and means of processing, where the data is hosted, how long it is retained, who can access it, and how data and accounts will be transferred or deleted if the service provider changes. Applicable privacy and data-protection obligations must be assessed for the intended markets.
The output of this stage
Schematic, PCB files, mechanical CAD, firmware build, preliminary BOM and design review record, as contractually agreed. The design review record is the evidence that the buyer reviewed the design and approved it — or asked for changes — before prototypes were built.
8. Build Prototypes and Manage Design Revisions
Prototypes have different purposes, and a buyer who treats them all as "samples" will approve the wrong thing at the wrong time.
Four kinds of prototype
| Prototype | Purpose |
|---|---|
| Proof-of-concept prototype | Demonstrates whether the idea or key function can work |
| Engineering prototype | Tests the main electrical, mechanical and firmware design |
| Design-validation sample | Checks whether the design meets the agreed requirements |
| Production-equivalent sample | Uses the intended production design, components and processes as closely as possible |
Avoid presenting these names as universally standardised stages. Different factories use different terminology. What matters is what each sample proves, not what it is called.
Manage every revision
- Give every sample a revision number.
- The revision record should also distinguish a correction of an existing defect from a change to an approved requirement. The factory should not automatically charge for correcting a failure to meet the agreed specification as if it were a buyer-requested design change; the contract should establish how these two situations are treated.
- Record hardware, firmware and BOM versions.
- Record test results and failures.
- Document changes made between revisions.
- Keep an approved reference sample.
- Do not approve a sample based only on appearance or a short demonstration.
A sample that works for five minutes on a desk has not been tested. The buyer should test each revision against the requirements matrix from Section 6, record the failures, and agree the changes before the next revision. The number of included revision rounds should be in the development contract from Section 5; additional rounds cost time and money, and the buyer should know whose money before the revisions start.
The output of this stage
A sample evaluation report, a revision history and an approved design baseline. The approved design baseline is the version of the hardware, firmware and BOM that the project will carry into validation. The baseline should identify the hardware revision, firmware version, BOM revision, tooling revision and test procedures in force at approval. The buyer should not approve "Sample V3" without knowing exactly what V3 contains. A baseline may need to be updated after validation failures; an updated baseline requires a new approval, not an informal change. Nothing changes after this point without the change procedure from Section 6.
9. Test and Validate the Product Before Production Approval
Verification and validation are different questions, and buyers sometimes confuse them.
- Verification asks whether the design meets the specified requirements.
- Validation asks whether the product meets the intended user needs and use conditions.
A product can pass verification and fail validation: it meets every line of the specification, but users cannot pair it, the battery dies in cold weather, or the app crashes on the most common phone. Both questions need answers before production approval.
What to test
- Functional and performance testing.
- Electrical safety.
- EMC and radio testing.
- Thermal and battery testing.
- Drop, vibration and environmental testing.
- Reliability and endurance testing.
- Firmware and software testing.
- Interoperability and compatibility.
- User experience and usability.
- Packaging and transport testing.
- Battery safety assessment, battery transport requirements and UN 38.3 test documentation where applicable.
- App and cloud security testing, and privacy requirements for any personal data collected, where relevant.
The exact test plan must follow the product's intended use, destination markets and applicable requirements. For wireless products, do not assume that using a pre-certified radio module automatically makes the finished product compliant.
A pre-certified radio module does not certify the product
For the United States, a radio module certified as a modular transmitter under 47 CFR 15.212 may be used in a host product only if the installation meets the module grant's conditions and the grantee's integration instructions. For example, the requirements for a single modular transmitter under §15.212(a)(1) address matters including radio-frequency shielding, buffered modulation or data inputs, power-supply regulation, antenna arrangements and stand-alone testing. The buyer should obtain the module's FCC grant, identify its approved antenna configurations and integration instructions, and check whether the host product needs additional equipment authorisation. Host digital circuitry may be an unintentional radiator under Part 15, Subpart B. If it is not exempt under §15.103, the applicable equipment authorisation procedure must be determined under §15.101, which specifies Supplier's Declaration of Conformity or certification according to the device category. Intentional transmitters are generally subject to certification under §15.201 unless covered by an applicable existing approval. The buyer should also check RF-exposure conditions, antenna restrictions and any co-location or other integration limitations in the module grant. Do not assume that the module's FCC approval automatically covers every radio-frequency or digital function in the finished product. (47 CFR 15.212 — Modular transmitters; 47 CFR 15.101 — Equipment authorization of unintentional radiators; 47 CFR 15.201 — Certification of intentional radiators)
For the European Union, radio equipment must meet the essential requirements of the Radio Equipment Directive 2014/53/EU: protection of health and safety, electromagnetic compatibility, and effective and efficient use of the radio spectrum. The manufacturer retains responsibility even when it hires a third party to perform testing or prepare documentation. For the hypothetical Bluetooth sensor, the RED applies because it is radio equipment, but the specific conformity route depends on the product's radio characteristics and any harmonised standards used. The manufacturer must carry out a conformity assessment, issue an EU Declaration of Conformity, affix the CE marking and retain technical documentation for ten years.
An important point for overseas buyers is that the legal manufacturer is not necessarily the Chinese factory. Under Article 2(12) of the RED, a manufacturer includes a person or company that has radio equipment designed or manufactured and markets it under its own name or trademark. Therefore, if an overseas buyer commissions a Chinese factory to develop and manufacture a product and sells it under its own brand, the overseas buyer may be the legal manufacturer under EU law. The Chinese factory does not automatically assume that role simply because it performs the engineering and manufacturing. An importer established in the EU has separate obligations. Identify the legal manufacturer and importer for each intended market at the beginning of development, and allocate the testing, documentation and conformity-assessment work accordingly. A contract can allocate responsibilities between the parties, but it cannot remove statutory obligations from the entity that is legally the manufacturer.
Since 1 August 2025, cybersecurity essential requirements under Delegated Regulation (EU) 2022/30 have applied to defined categories of radio equipment, including internet-connected radio equipment, certain childcare equipment, toys covered by the Toy Safety Directive and wearable radio equipment, subject to the Regulation's scope and exclusions. Delegated Regulation (EU) 2023/2444 moved the application date from 1 August 2024 to 1 August 2025.
There is an important transition ahead. Regulation (EU) 2024/2847, the Cyber Resilience Act, generally applies from 11 December 2027. However, its Article 14 reporting obligations for actively exploited vulnerabilities and severe incidents affecting products with digital elements have applied since 11 September 2026. Delegated Regulation (EU) 2026/339 repeals Delegated Regulation 2022/30 with effect from 11 December 2027. For a product under development, assess both the current RED cybersecurity requirements and the forthcoming Cyber Resilience Act obligations, taking account of the product's connectivity, intended functions and applicable exclusions.
A Bluetooth device that sends data to a companion smartphone, which then connects to the internet, may fall within the RED delegated rules' definition of internet-connected radio equipment; indirect connectivity through another device should not be overlooked.
Consider compliance at the design stage, not at final testing
Product compliance must influence design from the beginning. The product's intended markets and product category determine many design decisions: the radio and antenna, the battery, the materials, the labelling and the documentation. For a rechargeable device with a lithium battery sold in the EU, Regulation (EU) 2023/1542 concerning batteries and waste batteries applies. Article 17 and Chapter VI of Regulation (EU) 2023/1542 have applied since 18 August 2024, except that Article 17(2) applies 12 months after the first publication of the list referred to in Article 30(2). Do not assume that every rechargeable battery in a consumer electronic device needs a battery passport: the passport obligation from 18 February 2027 applies to defined categories, including light means of transport batteries, industrial batteries above 2 kWh and electric vehicle batteries — a small sensor battery is unlikely to be in those categories. Battery removability and replaceability
Another EU requirement that should be considered during product design is Article 11 of Regulation (EU) 2023/1542. From 18 February 2027, it generally requires portable batteries incorporated into products placed on the EU market to be readily removable and replaceable by end-users throughout the product's lifetime. A battery is considered readily removable if it can be removed using commercially available tools, without proprietary tools, thermal energy or solvents. Specialised tools may be used only where they are provided free of charge with the product. The product must also be accompanied by understandable instructions and safety information on battery use, removal and replacement, with that information permanently available online.
Article 11(2) allows certain specified product categories to have batteries removable and replaceable only by independent professionals. The list was amended by Commission Delegated Regulation (EU) 2026/1770, which includes additional categories such as certain wearable devices, wireless thermometer probes designed for food contact during food preparation, and specified industrial telematics devices. For the categories in Article 11(2), points (a) and (c) to (h), the derogation applies only where it is required to ensure the safety of the user and the appliance. These are limited derogations, not a general exemption for connected electronic products.
Article 11(3) provides a full derogation from the end-user removability and replaceability obligations in Article 11(1) where continuity of power supply is necessary and a permanent connection between the product and battery is required to ensure the safety of the user and the appliance or, for products whose main function is collecting and supplying data, for data-integrity reasons. A Bluetooth sensor does not qualify merely because it collects data. The Commission's October 2026 guidance identifies continuous temperature and humidity monitoring for temperature-sensitive goods as a possible example, but clarifies that the derogation does not apply where data collection is only an additional feature or where non-volatile memory means that battery removal would not create a data-integrity risk.
For products placed on the market from 18 February 2027, Article 11(7) also requires portable batteries to be available as spare parts for at least five years after the last unit of the equipment model is placed on the market, at a reasonable and non-discriminatory price for independent professionals and end-users. Article 11(8) prohibits software from impeding replacement with a compatible battery or compatible key components.
Buyers should therefore consider battery access, enclosure design, fasteners, replacement procedures, spare-battery availability and firmware restrictions before the design is frozen.
Battery supply-chain due-diligence obligations under Chapter VII of Regulation (EU) 2023/1542 are scheduled to apply from 18 August 2027, following the postponement introduced by Regulation (EU) 2025/1561. These obligations do not apply to every economic operator: Article 47 currently exempts operators with net turnover below EUR 40 million in the financial year preceding the last financial year, provided they are not part of a group exceeding the applicable consolidated turnover threshold. On 24 November 2026, the European Parliament adopted its first-reading position in the Omnibus IV procedure, proposing to raise the Article 47 threshold from EUR 40 million to EUR 200 million. As at 28 November 2026, the procedure was still awaiting the Council's first-reading position, so this amendment had not yet entered into force. The EUR 40 million threshold therefore remained the applicable statutory threshold. Check the legislative position before publication because this exemption is subject to change. Check the battery category and the phased dates for the product, rather than assuming one rule covers every battery.
For China, be careful with CCC: the fact that a product is manufactured in China for export does not automatically mean CCC applies, and the fact that it is manufactured in China does not automatically exempt it where CCC applies to the domestic market. Check the catalogue entry and implementation rule for the exact product: the catalogue covers 17 categories and 106 product types, and in June 2026 SAMR and CNCA published a complete English edition of the CCC implementation rules. The compliance documents and how to check them are in How to Check Electronics Compliance Documents from China: CE, FCC, RoHS and Battery Test Reports.
The output of this stage
An approved validation plan, test reports, a corrective-action record and a design-validation approval. Every failed test should have a corrective action with an owner and a date. A test report with failures and no corrective actions is not a validation.
10. Prepare Tooling, BOM and Production Documentation
This is where the article transitions from engineering to manufacturing. The question changes from "does the design work?" to "can the factory build it, repeatedly, to the same standard?"
The production documentation package
- Final BOM and approved component manufacturers.
- Component specifications and alternatives.
- PCB fabrication and assembly files.
- Mechanical drawings and mould specifications.
- Tooling ownership, location and maintenance.
- Assembly instructions.
- Work instructions and process controls.
- Production test fixtures and software.
- Firmware programming and version control.
- Quality-control plan.
- Packaging specifications.
- Spare parts and service documentation.
- Firmware source and release binaries, where contracted.
- Firmware build instructions and toolchain versions.
- Mobile app source and release versions, where contracted.
- Cloud/backend documentation and account handover, where applicable.
- Test software and fixture documentation.
- Approved third-party software and licence records.
"Equivalent component" must not mean an undocumented substitution
Critical components should be controlled by manufacturer part number, approved manufacturer and revision, with any change subject to the engineering-change procedure. A factory that substitutes a cheaper capacitor, a different battery cell or an alternative Bluetooth chip without telling the buyer has changed the product. The buyer should agree which components are critical, which alternatives are pre-approved, and what happens when a component becomes unavailable. The quality-control method that checks the goods against this documentation is in How to Control Electronics Quality When Sourcing from China: From Golden Sample to Mass Production.
The output of this stage
A controlled production documentation package and an approved BOM. "Controlled" means version-numbered, approved and change-managed: the factory builds from this version, and any change goes through the procedure from Section 6.
11. Run a Pilot Production Build and Approve Production Readiness
The first production run should not simply be treated as mass production. A pilot run is a controlled test of the factory's ability to build the approved product using the intended production process.
What the pilot run should prove
- Pilot quantity and objectives: what the run is for, and how many units.
- Production-line setup and operator training.
- Assembly and test process validation.
- First-pass yield and failure analysis.
- Rework and scrap rates.
- Process capability where relevant.
- Traceability and serialisation.
- Packaging and final inspection.
- Open issues and corrective actions.
A pilot run should not pass merely because the factory successfully assembled a batch. Agree the acceptance criteria in advance: a minimum first-pass yield, a maximum permitted defect rate, rework and scrap limits, required traceability, test coverage, corrective-action closure, and approval of production tooling and fixtures.
The familiar EVT/DVT/PVT terminology is a useful industry framework, not a universal mandatory sequence: EVT (Engineering Validation Test) asks whether the engineering design works; DVT (Design Validation Test) asks whether the design meets the defined product requirements; PVT (Production Validation Test) asks whether the factory can manufacture the approved design consistently using the intended production process; MP (Mass Production) is the released product manufactured under controlled conditions. Different factories and industries use the terms differently. Present them as project-management terminology, not legal requirements or universal engineering law.
Packaging and transport testing belong in the pilot run: the packaging specification and the shipping method decide whether the product survives the journey. The method is in How to Package and Ship Electronics from China: A Practical Guide for Overseas Buyers.
Three approvals that buyers confuse
- Design approval: the product design meets the agreed requirements.
- Compliance approval: the product has completed the conformity assessment and testing required for the intended market.
- Production approval: the factory can consistently manufacture the approved product using controlled processes.
Production approval and market-compliance approval are separate decisions. A written production release authorises manufacturing under the approved baseline; it does not authorise the product to be placed on a market where the required conformity assessment, documentation or regulatory approval remains incomplete.
These are not interchangeable. A product can have design approval and still fail compliance testing, and it can pass compliance testing and still fail production approval because the factory cannot build it consistently. For general electronics projects, these three approvals are recommended project controls, not legally mandatory stages for every product. Regulated product categories may impose additional design-control and conformity requirements.
The key rule
Do not release mass production until the buyer has approved the product design, production BOM, manufacturing process and test results.
The output of this stage
A pilot-run report, an approved golden sample, a production-readiness checklist and a written production release. The golden sample is a physical reference for appearance, construction and workmanship. It must be linked to the approved BOM, firmware version, test procedures and other controlled documentation — it cannot by itself define every electrical, software, performance or internal component characteristic.
12. Protect the Product After Launch: Changes, Ownership and Future Production
The first production order is not the end of the project. The controls needed after launch decide whether the product stays manufacturable, supportable and owned by the buyer.
What to control after launch
- Engineering changes: the factory must notify the buyer in advance and obtain written approval before changing a critical component, material or design feature.
- Component obsolescence: what happens when a part goes end-of-life.
- Firmware maintenance and update access: who can update the firmware, and who holds the source code.
- Defect feedback from the field.
- Corrective and preventive actions.
- Spare parts and service support.
- Tooling maintenance and access.
- Source files and documentation backups.
- Rights to transfer production to another factory.
- Confidentiality and restrictions on unauthorised reuse.
- Product revisions and compatibility between batches.
This section links directly to article #202 on warranty and after-sales service: the design decisions and records made during development determine how easily the product can be supported, repaired and improved after launch. A product whose firmware source code sits only on the factory's server, whose tooling is unaccounted for and whose BOM has undocumented substitutions cannot be supported by anyone else. The method is in Electronics Warranty and After-Sales Service from China: A Practical Guide for Overseas Buyers.
The output of this stage
A product lifecycle plan, an engineering-change procedure and a complete handover package. The handover package is the full set of files and records another factory would need to build the product — the controlled production documentation from Section 10, plus build environments and software dependencies where relevant.
The Stage-Gate Process: One Table to Manage the Project
The article's most citable feature is the stage-gate table — the 8-Gate Electronics Product Development Framework. The process can be managed through eight approval gates: feasibility, requirements, design, prototype, validation, pilot production, production release and market release. Each gate requires defined deliverables and documented buyer approval before the project advances.
| Gate | Required deliverable | Buyer approval before proceeding |
|---|---|---|
| Feasibility | Feasibility report, preliminary BOM, budget and schedule | Technical and commercial go/no-go |
| Requirements | Product specification and acceptance criteria | Requirements baseline |
| Design | Engineering files, design review and risk assessment | Design review approval |
| Prototype | Identified sample, revision record and test report | Prototype approval |
| Validation | Approved test plan, test reports and corrective actions | Design-validation approval |
| Pilot | Pilot-run report, approved BOM and production documentation | Production readiness |
| Production release | Approved production baseline and engineering-change procedure | Written authorisation to begin controlled mass production |
| Market release | Applicable conformity-assessment records, test reports, technical documentation, declarations and required markings | Documented market-compliance sign-off by the responsible legal manufacturer before placing the product on the relevant market |
A gate should not pass while a critical safety, regulatory or performance failure remains unresolved.
Development Deliverables Checklist
Use this checklist when requesting a development proposal or reviewing a factory's quotation. Every item should have a named owner, a delivery date and a version number.
| Deliverable | When it is due |
|---|---|
| Product brief and preliminary requirements | Before requesting a quotation |
| Feasibility report and preliminary BOM | Feasibility gate |
| Development agreement and IP schedule | Before paying development fees |
| Approved product specification and requirements matrix | Requirements gate |
| Schematic, PCB files and mechanical CAD | Design gate |
| Firmware build and source code, as contracted | Design gate |
| Sample evaluation report and revision history | Prototype gate |
| Approved test plan | Before validation testing starts |
| Validation plan, test reports and corrective actions | Validation gate |
| Controlled production documentation and approved BOM | Pilot gate |
| Pilot-run report and golden sample | Pilot gate |
| Written production release | Release gate |
| Documented market-compliance sign-off and applicable conformity documentation | Before placing the product on each intended market |
| Handover package and lifecycle plan | After launch |
Frequently Asked Questions
How do I develop a new electronic product in China?
Start with a product brief, check feasibility, choose a factory with real engineering capability, sign a development agreement that allocates IP, freeze a testable specification, build prototypes in revision-controlled rounds, validate the design, prepare production documentation, run a pilot build and release mass production in writing. Each stage has a gate the buyer must approve before the project advances.
What is the difference between OEM, ODM and custom product development?
OEM means manufacturing to the buyer's design. ODM means adapting or developing a product using the manufacturer's design and engineering. Private label means selling an existing product under the buyer's brand. Custom development means engineering a new product or a substantial redesign for the buyer. Suppliers use the labels inconsistently; ask what work the factory will actually perform.
Can a Chinese factory develop a product from an idea or sketch?
Yes, if the factory has in-house engineering capability and the buyer provides a proper brief. A sketch alone is not a brief: the factory needs functions, performance targets, size, power, connectivity, target cost, volume and launch date before it can quote.
What information does a factory need to develop a new product?
The product brief from Section 2: purpose and users, markets, functions, reference products, size and materials, power and battery, connectivity and software, target price and cost, volume, launch date and operating conditions.
How long does electronics product development in China take?
There is no standard duration. It depends on the product's complexity, the number of revision rounds, the tooling, the testing and the certification required. The schedule should be agreed as milestones tied to the stage gates, with the time each gate needs, rather than as a single promised date.
What are EVT, DVT and PVT in product development?
A widely used industry framework: EVT (Engineering Validation Test) asks whether the engineering design works; DVT (Design Validation Test) asks whether the design meets the defined requirements; PVT (Production Validation Test) asks whether the factory can manufacture the approved design consistently. It is not a universal mandatory sequence or a legal standard, and different factories use the terms differently.
How much does it cost to develop a new electronic product in China?
There is no universal development-fee structure. The quotation should separate engineering and design fees, NRE charges, prototype charges, PCB and component costs, mould and tooling costs, test fixture costs, certification and laboratory costs, and software and firmware development. Ask whether the quotation includes the complete agreed deliverables or merely the factory's engineering time.
What is an NRE fee in electronics manufacturing?
A non-recurring engineering fee: a one-time charge for the engineering work that is not repeated for each unit produced. It should be tied to deliverables and payment milestones, and the contract should state what happens to the fee if feasibility fails.
Who owns the product design when a Chinese factory develops it?
It depends on the right and the contract. Under China's Patent Law, the patent-application right for a commissioned invention belongs by default to the party that made the invention, unless otherwise agreed. Under the Copyright Law and the software protection regulations, copyright in a commissioned work or commissioned software belongs by default to the commissioned party, unless the contract says otherwise. Paying for development does not by itself transfer ownership. The development contract must allocate each right expressly. The buyer should also confirm that the factory has obtained the necessary rights from its employees, subcontractors and other contributors.
Does paying a Chinese factory for product development give me ownership of the design?
No, not by itself. Ownership of patent-application rights, copyright in drawings and designs, and copyright in firmware and software each follow their own default rules, and all of them can be changed by contract. State the allocation in the development agreement and the IP schedule.
Who owns the mould and tooling paid for by the buyer?
The development agreement should expressly identify the legal owner of the physical tooling, rather than simply record who paid for it. If the contract is silent or inconsistent, ownership, possession and access rights may depend on the transaction and applicable law. Payment alone should not be treated as a substitute for a clear tooling-ownership clause.
Can I move my product to another factory after development?
You can move production if you have the necessary ownership rights or licences, together with the technical files, tooling rights and test procedures needed to build the product. The agreement should expressly give the buyer the right to manufacture through alternative suppliers where that is the intended arrangement. If the factory owns the design or holds the only copy of the source code, the buyer cannot move production without its cooperation.
What is the difference between an engineering sample and a production sample?
An engineering sample tests the main design. A production-equivalent sample uses the intended production design, components and processes as closely as possible. Do not approve mass production on an engineering sample.
How do I approve a product sample before mass production?
Test the sample against the requirements matrix, record the results and failures, agree the changes, and approve a specific revision by number — hardware, firmware and BOM versions included. Keep an approved reference sample. Do not approve on appearance or a short demonstration.
What is the difference between design verification and design validation?
Verification asks whether the design meets the specified requirements. Validation asks whether the product meets the intended user needs and use conditions. Both are needed before production approval.
What tests should an electronic product pass before mass production?
It depends on the product, its markets and its requirements: functional and performance, electrical safety, EMC and radio, thermal and battery, drop and environmental, reliability, firmware, interoperability, usability and packaging tests. The test plan must follow the intended use and destination markets.
What is a pilot production run?
A controlled first production run that tests whether the factory can build the approved product using the intended production process, at the intended yield, with traceability and final inspection. It is not mass production, and mass production should not be released until the pilot run is approved.
How do I prevent a factory from changing components after sample approval?
Control critical components by part number, approved manufacturer and change procedure, and require engineering-change notification before any change. The approved BOM is the baseline; anything else is a change that needs approval.
When should I consider CE marking, FCC equipment authorisation and other compliance requirements during product development?
At the requirements and design stages, not at final testing. The radio, antenna, battery, materials and labelling decisions made early decide whether the product can pass certification later.
Can I use a pre-certified wireless module in a custom electronic product?
Yes, but the module's certification covers the module, not the finished product. The host must meet the grant conditions and the grantee's integration instructions, and other host functions may need separate authorisation. For the EU, the finished product must still meet the Radio Equipment Directive's essential requirements.
Who is responsible for product compliance when a Chinese factory develops the product?
Responsibility depends on the product, the destination market and the economic operator's legal role. Under the EU Radio Equipment Directive, the legal manufacturer must ensure conformity, arrange the required conformity assessment, issue the EU Declaration of Conformity and retain the technical documentation. An overseas buyer that has the product developed and markets it under its own name or trademark may itself be the manufacturer, even when a Chinese factory performs all the engineering and production. The EU importer has separate obligations to verify compliance before placing the product on the market. The development contract should identify the responsible legal entity and specify who performs testing, prepares and holds the technical documentation, issues the declaration and maintains compliance after launch.
How can I protect my product idea before contacting a Chinese factory?
Use a China-focused NNN agreement covering non-disclosure, non-use and non-circumvention, and share only the information the factory needs to quote. Take advice on governing law, forum and enforceability for the specific transaction, and keep records of what was shared and when.
What happens if the factory discovers that the product is not technically feasible?
The feasibility stage should end with a written go/no-go recommendation. The development agreement should state what happens then: whether the buyer pays for the feasibility work done, whether the project stops, and who owns any work produced up to that point.
How many prototype revisions should be included in the development agreement?
Agree the number in the contract before development starts, and agree the cost of additional rounds. There is no standard number; it depends on the product's complexity. What matters is that the buyer knows whose money pays for the next revision before it starts.
What should be included in a product development agreement with a Chinese factory?
Scope and deliverables, NRE and prototype charges, payment milestones, included revision rounds, feasibility failure, IP ownership and licensing, confidentiality, tooling ownership, rights to use another factory, access to source files and documentation, and termination, handover and dispute provisions.
Conclusion
A successful product-development project with a Chinese factory requires more than a good idea and a low unit price. It requires a clear brief, a frozen specification, an agreed development contract, controlled samples and a documented production release.
The chain is short: brief the factory properly, check feasibility before paying, choose a factory that can actually engineer, agree the contract and the IP before the work starts, freeze testable requirements, review the design early, revise prototypes against the requirements, validate before approving, prepare the production documentation, prove the factory can build it in a pilot run, and release mass production in writing. The buyer who does this work keeps control of the requirements, the design, the budget, the schedule and the product's future. The buyer who skips it discovers, usually at the pilot run or the first shipment, that control was never agreed — only assumed.
Sources
- Patent Law of the People's Republic of China (amended 2020, in force 1 June 2021), Articles 6, 8 and 10 — service inventions; patent-application rights for commissioned and jointly made inventions; assignment. https://www.wipo.int/wipolex/en/legislation/details/21027
- Civil Code of the People's Republic of China, Articles 858–861 — risk allocation in technology development, commissioned and cooperative development inventions and rights to use and transfer technical know-how. https://english.taizhou.gov.cn/Government/LawsandRules/art/2023/art_4afa47a964b94a2c8bef075f8b9ade04.html
- Copyright Law of the People's Republic of China (amended 2020, in force 1 June 2021), Articles 18 and 19 — works for hire; ownership of copyright in commissioned works. https://www.chinajusticeobserver.com/law/x/copyright-law-of-china-20201111 (authentic text: https://www.wipo.int/wipolex/en/legislation/details/21065)
- Regulations on Computer Software Protection, Articles 11 and 13 — copyright ownership for commissioned software; software developed in the course of employment. https://www.wipo.int/wipolex/en/legislation/details/13396; also https://en.ncac.gov.cn/legislations/administrativelawsandregulations/201706/t20170622_57060.html
- Anti-Unfair Competition Law of the People's Republic of China (revised 2025, in force 15 October 2025), Article 10 — trade-secret definition. https://www.cnipa.gov.cn/art/2026/5/20/art_104_206437.html
- State Administration for Market Regulation, Provisions on the Protection of Trade Secrets (Order No. 126, in force 1 June 2026). https://www.samr.gov.cn/zw/zfxxgk/fdzdgknr/fgs/art/2026/art_a89ca909478b460595670fabe02b21d3.html
- 47 CFR 15.212 — Modular transmitters; conditions for single and split modular transmitters and limited modular approval. https://www.ecfr.gov/current/title-47/chapter-I/subchapter-A/part-15/subpart-C/section-15.212
- 47 CFR 15.101 — Equipment authorization of unintentional radiators. https://www.ecfr.gov/current/title-47/chapter-I/subchapter-A/part-15/subpart-B/section-15.101
- 47 CFR 15.201 — Certification of intentional radiators. https://www.ecfr.gov/current/title-47/chapter-I/subchapter-A/part-15/subpart-C/section-15.201
- Directive 2014/53/EU of the European Parliament and of the Council of 16 April 2014 on radio equipment — essential requirements, conformity assessment and CE marking. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32014L0053
- Delegated Regulation (EU) 2022/30 — cybersecurity essential requirements for defined categories of radio equipment. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32022R0030
- Delegated Regulation (EU) 2023/2444 — moved the application date to 1 August 2025. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32023R2444
- Delegated Regulation (EU) 2026/339 — repeals Delegated Regulation 2022/30 with effect from 11 December 2027. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32026R0339
- Regulation (EU) 2024/2847 — Cyber Resilience Act, generally applies from 11 December 2027; Article 14 reporting obligations from 11 September 2026. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32024R2847
- Regulation (EU) 2023/1542 of the European Parliament and of the Council of 12 July 2023 concerning batteries and waste batteries — conformity assessment and CE marking, substance restrictions, digital battery passport and supply-chain due diligence, phased by battery category. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32023R1542
- Regulation (EU) 2025/1561 — postponed battery supply-chain due diligence to 18 August 2027. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32025R1561
- Commission Delegated Regulation (EU) 2026/1770 of 14 July 2026 — derogations from the removability and replaceability requirements for portable batteries under Article 11(2) of Regulation (EU) 2023/1542. https://eur-lex.europa.eu/eli/reg_del/2026/1770/oj
- Commission Notice C/2026/5531 of 22 October 2026 — guidelines on the removability and replaceability of portable and LMT batteries under Regulation (EU) 2023/1542, including the data-integrity derogation, compatible batteries, spare parts and software restrictions. https://eur-lex.europa.eu/eli/C/2026/5531/oj
- European Parliament legislative resolution of 24 November 2026, P10_TA(2026)0382, procedure 2025/0130(COD) — first-reading position on Omnibus IV, including the proposed amendment to Article 47 of Regulation (EU) 2023/1542. https://www.europarl.europa.eu/RegData/seance_pleniere/textes_adoptes/definitif/2026/11-24/0382/P10_TA(2026)0382_EN.pdf
- China Compulsory Certification (CCC) — catalogue (17 categories, 106 product types) and implementation rules; complete English edition published by SAMR and CNCA in June 2026. https://www.samr.gov.cn/xw/sj/art/2026/art_c911ae106ceb49348402c0a424df6447.html
Sources accessed or checked on 28 November 2026; publication dates and the dates of the underlying market information vary.